Stream: cql
Topic: Date in MeasureReport Resource
Polina A. (Apr 11 2019 at 01:01):
Looking for input on the meaning of "date" field in MeasureReport resource. It's description says "When the report was generated". Should it be interpreted as the date on which this measure was calculated/evaluated or the date on which the MeasureReport resource was generated?
Lloyd McKenzie (Apr 11 2019 at 02:41):
It's the date the report was calculated. If you calculated the resport internally last week but didn't put it in resource form until today, the date would be last week.
Polina A. (Apr 11 2019 at 03:11):
@Lloyd McKenzie thank you for the answer. Wonder if it is worth making the description a bit more clear? I think, if instead of "generated" it was "evaluated" or "calculated" it would've been less ambiguous
Bryn Rhodes (Apr 11 2019 at 03:14):
@Polina A. , that's a great suggestion, can you submit a tracker?
Polina A. (Apr 11 2019 at 03:15):
@Bryn Rhodes sure thing, will do!
Last updated: Apr 12 2022 at 19:14 UTC