Grahame Grieve (Mar 06 2018 at 02:17):
One of the editors was without power yesterday due to the storm in the NE. They've requested permission to make this change post freeze - does FMG think this is ok?
Grahame Grieve (Mar 06 2018 at 02:18):
Device-Resources-Feb-2018-V1.1.xlsx
Lloyd McKenzie (Mar 06 2018 at 15:42):
Well, the key question is what the impact is on IGs. I'm not clear from looking at the spreadsheet what the proposed change is. However, there are two device-based CGs and device may appear in a few others. I'd have them raise the change on the committer's list (in descriptive rather than spreadsheet form). If no-one hollers after 24 hours, then give them the go-ahead.